13. Procedure Automation Lifecycle - Retirement
This chapter explains retirement of automated procedures and provides informative annexes on metrics, drawing conventions, and project front-end loading. By the end, you’ll understand:
- Retirement - when and how to retire automated procedures
- Management of Change - formal process for retirement
- Metric Examples (Annex A) - 7 example metrics for monitoring
- Model Drawing Philosophy (Annex B) - conventions for diagrams
- Front-End Loading (Annex C) - project development stages
Think of this chapter as the end of the lifecycle plus valuable reference materials for implementation.
13.1 Retirement Triggers
Automated procedures are retired when:
13.1.1 Trigger 1: Plant Retirement
Plant is retired:
- Facility closure
- End of plant life
- Permanent shutdown
Automated procedures retired with plant:
- No longer needed
- Equipment gone
- Process ended
Example:
Refinery closes after 40 years → all automated procedures for that refinery retired.
13.1.2 Trigger 2: Process Changes
Process changes made:
- Different raw materials
- New product line
- Modified process
- Equipment changes
AND procedures no longer apply:
- Logic based on old process
- Equipment doesn’t exist
- Process parameters different
- Procedure obsolete
Example:
Chemical plant switches from batch to continuous process → all batch startup procedures no longer apply → retire batch procedures.
13.1.3 Trigger 3: Control System Upgrade/Replacement
When BPCS upgraded or replaced:
Automated procedures may need to be:
Upgraded:
- Migrated to new platform
- Reconfigured for new system
- Updated for new capabilities
- Modernized
OR retired and replaced:
- Too old to migrate
- Platform incompatible
- Opportunity for redesign
- Complete replacement better
Example:
Plant upgrades from old DCS to modern DCS:
Option 1 - Upgrade:
Convert existing procedures to new platform, test, deploy.
Option 2 - Retire and replace:
Retire old procedures, design new procedures leveraging modern capabilities, implement fresh.
Decision based on:
- Migration cost vs. replacement cost
- Opportunity for improvement
- Compatibility
- Strategic direction
13.2 The Decision Process
The decision to retire automated procedure:
Will be defined through:
Appropriate Management of Change (MOC) work processes.
Why MOC required?
Retirement is significant change:
- Affects operations
- May impact safety
- Requires review
- Needs approval
- Documentation required
MOC ensures:
- Proper evaluation
- Risk assessment
- Stakeholder review
- Formal approval
- Documented decision
- Alternative plans
- Training updated
Cannot just delete procedures - formal process required!
13.3 Maintaining Retired Procedures
If automated procedure is retired:
A copy should be maintained:
To facilitate future reuse.
Why keep retired procedures?
13.3.1 Reason 1: Historical Reference
Understanding past operation:
- How did we do it?
- Why was it designed this way?
- What worked?
- What didn’t work?
13.3.2 Reason 2: Knowledge Preservation
Expertise captured:
- Engineering knowledge
- Operational experience
- Design decisions
- Lessons learned
Don’t lose institutional knowledge!
13.3.3 Reason 3: Future Reuse
Potential reuse scenarios:
Similar project:
- New similar unit
- Expansion
- Duplicate facility
- Starting point for new design
System upgrade:
- Migrate to new platform
- Reference for redesign
- Understand original intent
Troubleshooting:
- Compare old vs. new
- Understand changes
- Historical context
Knowledge mining:
- Extract design patterns
- Reuse logic modules
- Best practices
- Proven approaches
Example reuse:
Plant A retires distillation startup procedure when switching to continuous operation. Five years later, Plant B building new batch distillation → uses Plant A’s retired procedure as starting point → saves months of development!
Retired doesn’t mean deleted - archived for value!
13.4 Requirement
The Procedure Owner shall ensure:
That appropriate Management of Change work processes SHALL BE:
- Defined - MOC process exists
- Used - MOC process followed
To retire an automated procedure.
What this means:
Must have:
- Formal MOC process for retirement
- Process documented
- Process followed
- Approval obtained
- Documentation complete
Cannot:
- Informally retire procedures
- “Just turn it off”
- No review or approval
- Undocumented decision
Procedure Owner accountable.
Why mandatory?
Without MOC:
- Uncontrolled changes
- Safety risks
- No documentation
- Lost knowledge
- Poor decisions
With MOC:
- Controlled process
- Risk assessed
- Documented
- Approved
- Knowledge preserved
Retirement = significant change requiring formal management!